1. To review/approve/reject the SPC Control Limit, user can go to Production > Production Control > Approval List.

Image 1

2. User can click the first icon to review the newly calculated spc control limit before approve or reject it.

Image 2

3. After user has reviewed and decided to REJECT the spc control limit, user can click the second icon on the left bottom to redirect to reject the SPC Control Limit.

Image 3

4. User can then click the Re-Calculate button to REJECT and RESET the SPC Control Limit.

Image 4

5. On the other hand, user can tick the New SPC Control Limit Value option to enter new values and calculate for new SPC Control Limit instead of reject the current SPC Control Limit.

Image 5

6. After user has entered the new SPC Control Limit Value, user can click the Re-Calculate button and system will prompt a message to ask for confirmation.

Image 6

7.  If the 1st level user chooses to REJECT the SPC Control Limit with NEW VALUE, system will update the SPC Control Limit and system will acknowledge the action as Approve and send it to user from level 2 and above for further approval.