SPC Control For Existing Product

Creation date: 4/19/2024 5:28 AM    Updated: 4/19/2024 5:32 AM   control limit limit line conversion recalculate spc control

1. For existing product, when user did not tick to recalculate the SPC Control Limit, system will not trigger for approval and use the previous control limit, and user will be able to start the line conversion for another work order that is using the same product.


Image 1

2. User can go to Production > Production Control > SPC Control Limit Review to re-calculate the SPC Control Limit. Only the user set in Approval Routing is able to re-calculate the SPC Control Limit


Image 2

3. If user choose to re-calculate the SPC Control Limit, the SPC Control Limit will be reset and user will have to re-enter 30 points to recalculate the SPC Control Limit.


Image 3


Image 4

Action Required: User